Week 4 we are progressing approx. 3 days ahead of programme for our client. Prepping for 1100m2 of surfacing base and wearing course by end of week, bring on the road marking. Also commencing with concrete slabs this week.


Our client is very happy with our Labour as well as our plant including LFS 2019 8t komatsu excavator.


39 views0 comments

We will be completing all foundation pours for the new teaching block by end of this week





50 views0 comments

Updated: Mar 25, 2019

Phase 2 now ongoing at Hackney Wick with part 1 of 3 parts for externals handed over yesterday enabling access to block b for those people moving into the apartments this week.

Excellent Tobermore brickwork finishing off this great project.





54 views0 comments