Cherwell project for Kier at Banbury

Week 4 we are progressing approx. 3 days ahead of programme for our client. Prepping for 1100m2 of surfacing base and wearing course by end of week, bring on the road marking. Also commencing with concrete slabs this week.


Our client is very happy with our Labour as well as our plant including LFS 2019 8t komatsu excavator.